Oracle’s $165 Billion Data Center Plan Hits a Gas Pipeline Delay

Oilprice.com · 54m ago · 🇺🇸 United States
Oracle’s $165 Billion Data Center Plan Hits a Gas Pipeline Delay

Oracle’s proposed $165 billion data center project in New Mexico has run into a decidedly low-tech problem: the natural gas pipeline meant to help power it won’t be ready on time. Energy Transfer subsidiary Transwestern Pipeline pushed the expected in-service date for its Green Chile Project from August 15 to February 1, 2027, according to a regulatory filing Friday. That six-month delay threatens the schedule for Oracle’s Project Jupiter, a proposed data center development in Doña Ana County near the U.S.-Mexico border.…